NT · Isolated northern systems · 2023
Several isolated hydro and diesel systems, not one grid. Taltson expansion is the nation-building file. Full dossier not in this edition.
| 2023 | 2026 | 2030 | 2035 | 2050 | |
|---|---|---|---|---|---|
| Generation TWh | 0.7 | 0.7 | 0.8 | 0.8 | 0.9 |
| End-use electricity TWh | 0.7 | 0.7 | 0.8 | 0.8 | 0.9 |
| Capacity GW | 0.3 | 0.3 | 0.3 | 0.4 | 0.4 |
| Gen − end-use TWh | -0.0 | 0.0 | 0.1 | 0.1 | 0.1 |
Same workbook for every jurisdiction. Residual ≠ surplus. Source: CER EF2026.
No connection to Alberta, BC, or the North American bulk system.
Among the highest in Canada; Territorial Power Support Program caps a block of kWh at Yellowknife rates.
Operator: Northwest Territories Power Corporation. Regulator: NWT Public Utilities Board. This page will take the same skeleton as Quebec, Ontario, Alberta, and B.C. without a redesign.
| Metric | 2023 | Note |
|---|---|---|
| Generation | 0.69 TWh | CER EF2026 |
| Capacity | 269.8 MW | includes storage where reported |
| End-use electricity | 0.7 TWh | converted from PJ |
| Net international exports | — | positive = export |
| Interprovincial in-flows | — | Quebec’s in-flow is mostly Churchill Falls |