NB · Vertically integrated Crown · 2023
The Maritimes’ nuclear-and-ties hub: Point Lepreau, Quebec in, Nova Scotia and New England out. Full dossier not in this edition.
| 2023 | 2026 | 2030 | 2035 | 2050 | |
|---|---|---|---|---|---|
| Generation TWh | 13.9 | 14.0 | 13.3 | 13.2 | 14.2 |
| End-use electricity TWh | 13.7 | 13.3 | 13.5 | 14.1 | 16.7 |
| Capacity GW | 4.5 | 4.9 | 5.3 | 4.7 | 5.3 |
| Gen − end-use TWh | 0.2 | 0.8 | -0.2 | -0.9 | -2.4 |
Same workbook for every jurisdiction. Residual ≠ surplus. Source: CER EF2026.
Quebec 1,029 / 785 MW; US 1,145 / 719 MW; Nova Scotia 150 / 194 MW; PEI 300 / 170 MW.
Mid-to-high provincial residential rates.
Operator: NB Power. Regulator: New Brunswick Energy and Utilities Board. This page will take the same skeleton as Quebec, Ontario, Alberta, and B.C. without a redesign.
| Metric | 2023 | Note |
|---|---|---|
| Generation | 13.90 TWh | CER EF2026 |
| Capacity | 4,509.4 MW | includes storage where reported |
| End-use electricity | 13.7 TWh | converted from PJ |
| Net international exports | +2.5 TWh net export | positive = export |
| Interprovincial in-flows | 6.7 TWh | Quebec’s in-flow is mostly Churchill Falls |